OK TEDI SUCCESSFUL COMPLETION OF UNDERGROUND PUMP STATION PROJECT

Ok Tedi Mining Limited has successfully completed the construction of a critical underground pump station project, that will improve mine water management, enhance safety and save significant cost.

Managing Director and Chief Executive Officer Kedi Ilimbit congratulated the team for successfully completing the project.

“As a world class mine, it is imperative that we adopt global best practices. The underground pump station is among a number of projects undertaken by Ok Tedi to improve operational efficiency within our mine operation to ensure we continue to deliver results for the benefit of our shareholders, the people of Western Province and Papua New Guinea,” Ilimbit said.

The project led by Manager Mine Support Service and Underground James Waisime, was delivered collaboratively by mining engineers, geotechnical engineers, structural engineers, surveyors, boilermakers, pump fitters, electricians and underground miners from the Mine Operations business unit and Major Project Engineering Team.

Waisime said, “this was a true team effort; the safe and timely completion of this project demonstrates the strength of collaboration across departments and our contractors. I’m proud of the commitment and professionalism shown by everyone involved.”

According to OTML, the project, started in August 2024 and was completed in June 2025, without any incident and below its projected cost with a saving of USD$1.2 million, highlighting Ok Tedi’s commitment to safety and operational excellence.